Saturday, February 27, 2010

stand still

well for the past 2 weeks nothing much has happened...

The painter did start on Monday but done 1 day and then stopped. Hopefully he will be their tomorrow.

The site supervisor i had got a new job, so now i have a new site supervisor, i have not had contact from him yet.

I am pretty disappointed that the house has basically sat there for the last 2 weeks with no action...

I am going to call coral tomorrow to try and get a PCI date at least...

I noticed yesterday that our water tank turned up

Tuesday, February 16, 2010

lots of photos




































Painting is next, just waiting on the call from the painter...
The picture beside is my little boy lachlan who started kindy this year in my walk in

Monday, February 8, 2010

Wet area's are being tiled

We had a meeting with our tile man today, he has started and was happy to add in our feature tile. (We picked these up on the gold coast, thank god for tile mart we keep feature tiles in stock)

Wednesday, February 3, 2010

Kitchen in...

The kitchen was put in today, will post some pictures tomorrow as it was to dark to get photos.

They have also put in the down pipes, architraves, and the doors...

cant wait to see what they do tomorrow...

Monday, February 1, 2010

wet area's sealed and leaking roof

No post last week as only the cornices were done,

We have had a bit of rain over the week end which brought our attention to a leaking roof, we have let the SS know so hopefully will be fixed.

Been up to the house today and the wet area's are being sealed. The Fit stuff is starting to be delivered.