Tuesday, December 15, 2009

Frame and Roof on in 2 days











The frame went up yesterday with the roof going on today... It is moving quick now.. Only 5 days before they shut down to Christmas..








Seeing the rooms now, I think i would change a few things, but i will wait and see. I will be happy with it anyway.








I am really happy with how fast they are doing stuff, they even worked in the rain today.

Friday, December 11, 2009

We have a Slab


Well its been 3 weeks since our site start date and we have a slab..


Called around to the house at lunch time and the site supervisor was there. He advised that the windows are getting delivered tomorrow and the frame on Monday, They will have the frame up on Monday and Tuesday and then will have the roof on and the tiles on the roof by Christmas. They will be working right up to the 23rd of December and be back at it on the 11th January. I am really happy with how quick it is now going to go.

Tuesday, December 1, 2009

Screw Piers...


They are back at work, today in went the screw piers.